News Stories

Results:
Tag: NJDEP
Clear
  • November

    Army Corps shares update on Absecon Island beachfill

    The U.S. Army Corps of Engineers (USACE) Philadelphia District shared an update regarding periodic nourishment of the Absecon Island dune and beachfill project in New Jersey. USACE awarded a contract to Great Lakes Dredge & Dock Company of Houston, Texas for $38.2 million to complete periodic nourishment of the project. The contract calls for dredging and placing 1.2 million cubic yards of sand onto the beaches of Absecon Island.
  • October

    Army Corps shares update for periodic nourishment of Lower Cape May Meadows-Cape May Point project

    The U.S. Army Corps of Engineers’ Philadelphia District shared an update regarding periodic nourishment for the Lower Cape Meadows-Cape May Point project in New Jersey. In September 2024, USACE awarded a contract to Agate Construction Company, Inc. of Egg Harbor Township, NJ for $1.3 million. The contract calls for ‘backpassing’, which means sand will be excavated from areas along the beach instead of dredging the sand from offshore borrow areas or inlets. The base contract work will involve excavating approximately 88,000 cubic yards of sand from beach areas that have accumulated excess sand. This sand will then be placed at the Cove Beach area in the City of Cape May.
  • September

    Army Corps awards contract for Cape May City beachfill project

    The U.S. Army Corps of Engineers’ Philadelphia District awarded a contract to Great Lakes Dredge & Dock Company of Oak Brook, Ill. for $16.1 million to complete periodic nourishment of the Cape May Inlet to Lower Township (Cape May City) Coastal Storm Risk Management project. The project is a joint effort of the Army Corps’ Philadelphia District, the U.S. Coast Guard, and the New Jersey Department of Environmental Protection.
  • May

    Army Corps awards contract for Brigantine beach nourishment

    The U.S. Army Corps of Engineers’ Philadelphia District awarded a contract to Norfolk Dredging Company for $14 million to conduct periodic nourishment of the Brigantine dune and berm Coastal Storm Risk Management project. The project is a joint effort between the U.S. Army Corps of Engineers, the New Jersey Department of Environmental Protection, and the City of Brigantine.
  • March

    U.S. Army Corps of Engineers, New Jersey Department of Environmental Protection announces start of work on Union Beach Coastal Storm Risk Reduction Project

    NEW YORK — The U.S. Army Corps of Engineers (USACE), New York District, in partnership with the New Jersey Department of Environmental Protection (NJDEP) announces the start of construction work for the Union Beach Coastal Storm Risk Reduction Project. The first contract, which represents phase 1 of this coastal storm risk reduction project, was awarded to Weeks Marine, Cranford, N.J. in the amount of $50,035,435. The project will include construction of a beach berm with a planted dune, pedestrian, and vehicle crossovers, as well as two terminal groins. The project occupies approximately 1.8 square miles along the coast of Raritan Bay in the northern portion of Monmouth County, New Jersey.
  • January

    Army Corps awards contract for Avalon and Stone Harbor beach nourishment

    The U.S. Army Corps of Engineers’ Philadelphia District has awarded a contract to Great Lakes Dredge & Dock Company of Oak Brook, IL for $28.8 million to conduct periodic nourishment of the Townsends Inlet to Cape May Inlet (Avalon & Stone Harbor) dune and beachfill project. The project is a joint effort between the U.S. Army Corps of Engineers, the New Jersey Department of Environmental Protection, and the boroughs of Avalon and Stone Harbor.
  • October

    Army Corps awards contract for periodic nourishment of Ocean City beachfill project

    The U.S. Army Corps of Engineers’ Philadelphia District has awarded a contract to Great Lakes Dredge & Dock Company of Oak Brook, IL for $21.5 million to conduct periodic nourishment of the Great Egg Harbor and Peck Beach, (Ocean City), NJ project in New Jersey. Work is the result of a partnership between the Army Corps’ Philadelphia District, the New Jersey Department of Environmental Protection, and Ocean City.
  • August

    Army Corps releases draft report for New Jersey Back Bays study

    The U.S. Army Corps of Engineers has announced the release of a draft report for the New Jersey Back Bays Coastal Storm Risk Management Study. The report outlines a ‘Tentatively Selected Plan’ framework, which includes three storm surge barriers, two cross-bay barriers, and the elevation of more than 18,000 structures to reduce the risk of flood damages associated with storm surge. It’s important to note that the plan is subject to change. It has not yet been approved by higher authorities, including Congress, and has not been funded for implementation at the federal or state level.
  • Army Corps releases draft report for New Jersey Back Bays study

    The U.S. Army Corps of Engineers has announced the release of a draft report for the New Jersey Back Bays Coastal Storm Risk Management Study. The report outlines a ‘Tentatively Selected Plan’ framework, which includes three storm surge barriers, two cross-bay barriers, and the elevation of more than 18,000 structures to reduce the risk of flood damages associated with storm surge. It’s important to note that the plan is subject to change. It has not yet been approved by higher authorities, including Congress, and has not been funded for implementation at the federal or state level.
  • April

    Army Corps constructs beach access with innovative flood barrier in Seaside Heights

    The U.S. Army Corps of Engineers and its contractor completed construction of a vehicular access in Seaside Heights, NJ where the beach meets the boardwalk at Grant Avenue. The access includes a removable coastal flood barrier, which can be quickly installed prior to a storm. The vehicular access and removable barrier are part of the 14-mile dune and beachfill project along the Barnegat Peninsula in Ocean County, NJ.
  • May

    Army Corps announces signing of Chief’s Report for New Jersey study

    The U.S. Army Corps of Engineers’ Philadelphia District announces that Lt. Gen. Todd T. Semonite, USACE Commanding General and the 54th U.S. Army Chief of Engineers, has signed the Chief’s Report for the “New Jersey Beneficial Use of Dredged Material for the Delaware River Feasibility Study” — a significant milestone for the proposed project. The signing of the report advances the project to Congress for authorization.
  • September

    Army Corps awards contract for Seven Mile Island beachfill

    The U.S. Army Corps of Engineers’ Philadelphia District awarded a contract to Great Lakes Dredge & Dock Company of Oak Brook, Ill. for $7.5 million to complete periodic nourishment of the Townsends Inlet to Cape May Inlet (Avalon and Stone Harbor) Coastal Storm Risk Management project. The project is a joint effort of the Army Corps’ Philadelphia District, the New Jersey Department of Environmental Protection and the communities of Avalon and Stone Harbor.
  • July

    Army Corps awards contract for Cape May City beachfill project

    The U.S. Army Corps of Engineers’ Philadelphia District awarded a contract to Great Lakes Dredge & Dock Company of Oak Brook, Ill. for $7.6 million to complete periodic nourishment of the Cape May Inlet to Lower Township (Cape May City) Coastal Storm Risk Management project. The project is a joint effort of the Army Corps’ Philadelphia District, the U.S. Coast Guard, and the New Jersey Department of Environmental Protection.
  • May

    District celebrates completion of Absecon Inlet seawall and boardwalk

    The U.S. Army Corps of Engineers’ Philadelphia District joined elected officials and partners on May 25, 2018 to celebrate the completion of the Absecon Inlet seawall and boardwalk rebuild in Atlantic City. The project – one of the more complex construction efforts undertaken by the District in recent years – involved building two separate seawall structures along approximately 1700 feet of the inlet and rebuilding the historic boardwalk.
  • Philly District celebrates completion of Absecon Inlet seawall and boardwalk

    The U.S. Army Corps of Engineers’ Philadelphia District joined elected officials and partners on May 25, 2018 to celebrate the completion of the Absecon Inlet seawall and boardwalk rebuild in Atlantic City. The project – one of the more complex construction efforts undertaken by the District in recent years – involved building two separate seawall structures along approximately 1700 feet of the inlet and rebuilding the historic boardwalk.
  • Philly District, Atlantic City officials celebrate completion of Absecon Inlet seawall and boardwalk

    The U.S. Army Corps of Engineers’ Philadelphia District joined elected officials and partners on May 25, 2018 to celebrate the completion of the Absecon Inlet seawall and boardwalk rebuild in Atlantic City. The project – one of the more complex construction efforts undertaken by the District in recent years – involved building two separate seawall structures along approximately 1700 feet of the inlet and rebuilding the historic boardwalk.
  • November

    Army Corps, NJDEP to host public meeting for flood risk study

    The U.S. Army Corps of Engineers and the New Jersey Department of Environmental Protection are hosting a public meeting regarding the New Jersey Back Bays Flood Risk Management study on Dec. 1 from 6-8 p.m. at Stockton University in Galloway Township, N.J.
  • January

    Army Corps, state announce change to beachfill schedule for Strathmere

    PHILADELPHIA (JAN 15, 2015) – Reconstruction of the beach on Ludlum Island this spring will begin at the northernmost end of Strathmere after all, the U.S. Army Corps of Engineers and the New Jersey Department of Environmental Protection announced today.
  • Army Corps, state announce change to beachfill schedule for Strathmere

    PHILADELPHIA (JAN 15, 2015) – Reconstruction of the beach on Ludlum Island this spring will begin at the northernmost end of Strathmere after all, the U.S. Army Corps of Engineers and the New Jersey Department of Environmental Protection announced today.
  • December

    Army Corps awards contract to complete construction of Long Beach Island dune project

    The U.S. Army Corps of Engineers’ Philadelphia District awarded a contract Dec. 5 to the Great Lakes Dredge and Dock Company for $128 million to complete the initial construction of the Long Beach Island Coastal Storm Damage Reduction project in New Jersey. The project is a joint effort of the Army Corps’ Philadelphia District and the New Jersey Department of Environmental Protection.
  • Army Corps awards contract to complete construction of Long Beach Island dune project

    The U.S. Army Corps of Engineers’ Philadelphia District awarded a contract Dec. 5 to the Great Lakes Dredge and Dock Company for $128 million to complete the initial construction of the Long Beach Island Coastal Storm Damage Reduction project in New Jersey. The project is a joint effort of the Army Corps’ Philadelphia District and the New Jersey Department of Environmental Protection.
  • November

    Army Corps awards contract for Southern Ocean City, Strathmere and Sea Isle beachfill

    PHILADELPHIA (November 10, 2014) - The U.S. Army Corps of Engineers awarded a $57.6-million contract to the Great Lakes Dredge and Dock Company for a coastal and storm damage reduction project extending from the southern end of Ocean City to Strathmere and Sea Isle. The project, which entails the construction of a dune and a berm, or beach, in front of each community, is a joint effort of the Army Corps’ Philadelphia District and the New Jersey Department of Environmental Protection.
  • Army Corps awards contract for Southern Ocean City, Strathmere and Sea Isle beachfill

    PHILADELPHIA (November 10, 2014) - The U.S. Army Corps of Engineers awarded a $57.6-million contract to the Great Lakes Dredge and Dock Company for a coastal and storm damage reduction project extending from the southern end of Ocean City to Strathmere and Sea Isle. The project, which entails the construction of a dune and a berm, or beach, in front of each community, is a joint effort of the Army Corps’ Philadelphia District and the New Jersey Department of Environmental Protection.
  • February

    Army Corps and contractor to begin repairing Barnegat Inlet Jetty

    The U.S. Army Corps of Engineers’ Philadelphia District awarded a contract to repair the north jetty at Barnegat Inlet, which protects the southern tip of state-owned Island Beach State Park. The work is part of a larger effort to repair USACE projects damaged by Hurricane Sandy. The contract was awarded to Agate Construction Company of Clermont, N.J. for $7.6 million to repair approximately 740 feet of the jetty on the north side of the inlet that was damaged due to Superstorm Sandy. The project is expected to begin later this month and extend to the fall.
  • June

    Army Corps, NJDEP sign cost-sharing agreement to officially begin a reevaluation of comprehensive flood risk management solutions for the Passaic River Basin

    NEW YORK – The U.S. Army Corps of Engineers, New York District, and the New Jersey Department of Environmental Protection have both signed a cost-sharing agreement that officially begins the Passaic River Basin General Reevaluation Study, analyzing and comparing flood risk management alternatives for communities throughout the basin. The reevaluation is one of the 15 recommendations made by New Jersey Governor Chris Christie’s Passaic River Flood Advisory Commission.